State Route 125 Closed For Culvert Replacement

The Ohio Department of Transportation has announced a culvert replacement on St. Rt. 125 requires a full closure for 19 days.

Beginning 8 a.m. Wednesday, July 19, SR 125 will be closed at Spring Grove Road until 7 p.m. Monday, August 7.

The detour will use SR 125 to SR 774 to SR 133 and SR 125.

Arrow boards and/or signs will be in place to alert motorists of the upcoming work zone and restrictions.

To help ensure the safety of the construction workers as well as the traveling public, motorists should remain alert, reduce their speed and watch for stopped traffic while passing through the work zone.

Summer Road Closures Scheduled

In order to replace culvert pipes on Donald Rd and Antioch Rd, the Clermont County Engineer’s Office has notified Tate Township of these closings with detours.  Signs will be placed to notify residents and give detours.

Donald Rd will be closed to through traffic on Monday 7/17- Thursday 7/20 from 7AM to 5PM between addresses 2118 & 2150 Donald Rd.  Two culverts will be replaced.  The detour will be 8.19 miles.

Antioch Rd will be closed to through traffic on Wednesday 7/19 – Monday 7/24 from 7AM to 5PM with the work starting between addresses 1842 & 1859 Antioch Rd.  Two culverts will be replaced.  The detour will be 4.37 miles.

Cemetery Safety Concerns

Please keep in mind that due to safety concerns for our mowing crews, all shepherd hooks and hanging ornaments as of January 1st, 2017 had to be removed from the cemetery.

All the shepherd hooks and solar lights have been tagged with the plot information and retained.  If you would like your shepherd hook, please call (513)734-2384 to arrange a pick-up time and date.  The remaining shepherd hooks that are not picked up will be disposed of after 10/01/17.  As of October 1st, 2017, any newly placed hooks, poles, or other dangerous decorations will be removed and disposed of.

Thank you for adhering to this cemetery rule because the safety of our mowing crew is very important to us.